Quick answer

Building a new home in Northbrook means a $10,000 demolition tax if you tear down, a sealed civil engineering set with on-site drainage, a look-alike review of your elevations, a sprinkler permit, and building fees of $3 per square foot of floor area. Each requirement comes from the Village of Northbrook's own permit pages, which list the demolition tax, deposits and submittals for a new single-unit residence.

Key takeaways

  • Check the lot before you make an offer. Northbrook's civil engineering rules need topography 25 feet into the neighbors' lots and a survey of every tree 6 inches or larger, so drainage and trees decide what the lot can hold.
  • Budget about $15,750 in village charges for a teardown before the new house is permitted. That is the $10,000 demolition tax and $750 in fees, plus a $5,000 deposit you get back after the final demolition inspection.
  • Plan for stormwater from the first sketch. Every new home needs an on-site drainage system, and 1,000 square feet or more of new hard surface triggers underground detention, so the house footprint and driveway shape the engineering.
  • Design the front of the house with the neighbors in mind. The monotony review compares your elevations with the three houses on each side and the one across the street, and any later change to the exterior goes back for review.
  • File the sprinkler permit with the building permit. Sprinklers are required in every new house, and the rough framing inspection cannot be scheduled until the sprinkler permit is issued.

Planning a project in Chicago or on the North Shore? Request a consultation and our team will follow up within one business day.

Our team has designed and built in Northbrook, including Leisure Point, a ground-up home we took from lot evaluation to move-in, and a second Northbrook home is under construction now. What we tell every family starting here is that the house is rarely the hard part. The village is clear and well organized, but it asks for a lot before the first footing is poured: a demolition tax, a full civil engineering set, a look-alike review of your elevations and a sprinkler permit. This guide walks through those steps in the order you will meet them, with each rule taken from the Village of Northbrook's own pages.

Before you buy: what the lot has to tell you

Most new homes in Northbrook replace an older ranch or split-level, so the lot usually comes with a house, mature trees and drainage patterns the neighbors depend on. Three things decide what the lot can hold, and all three can be checked before you make an offer.

  • Drainage. The village's civil engineering submittal guidelines (revised 2026) require topography in 1 foot contours across your lot and at least 25 feet into the neighboring properties. If the lot sits low, the grading plan has to solve it.
  • Trees. The same guidelines require a survey of every tree 6 inches or more in diameter, measured 4 1/2 feet above the ground, on your lot, 25 feet into the neighbors' lots and across the village right-of-way. Every removal must be approved by the Village Tree Preservation Officer before it happens.
  • Floodplain. Lots in the regulatory floodplain need a floodplain development permit, elevation certificates and, where it applies, a storage analysis, per the same guidelines.

When families bring us a lot they are considering, we walk it with them and tell them what it can hold. Our build on your lot page explains how we evaluate one.

Step one: the teardown and the $10,000 demolition tax

Northbrook's residential demolition page lists three charges due when the demolition permit is issued: a demolition tax of $10,000 for every single-unit residential demolition permit applied for since January 1, 2021, building construction and inspection fees of $750, and a $5,000 right-of-way damage deposit and demolition escrow, refunded after the final demolition inspection is approved.

The paperwork matters as much as the money. The same page requires a demolition management site plan showing chain-link construction fencing, wood slat tree fencing and every utility to be disconnected, plus a Cook County demolition permit, letters from ComEd and Nicor Gas confirming disconnection, a tree removal permit application and verification of the final water meter reading. In our projects, the utility letters are what most often hold a demolition date, so we request them early. Our teardown and rebuild page covers how we plan the demolition itself.

Step two: civil engineering and stormwater

Every new house in Northbrook needs its own civil engineering drawings, sealed by a licensed engineer and submitted separately from the architectural set. The new single-unit residence page says plainly not to combine the two into one plan set.

The civil guidelines spell out what reviewers look for:

  • An on-site drainage system for every new single-family home, connected to existing storm sewer, extended to it, or held on site with restricted outflow where drainage is substandard.
  • Underground detention when new impervious surface on the property reaches 1,000 square feet or more, with a stormwater management report sealed by the engineer.
  • Downspouts aimed at the front or rear property line, splashing on grade, never toward a neighbor.
  • A 40 percent cap on impervious coverage in the front yard, and driveways kept 2 feet from interior property lines.

There is also a fee for new hard surface. The village's impervious coverage fee sheet charges $1.60 per square foot in areas without stormwater detention, $0.80 in areas that meet some detention requirements, and nothing where detention was built with the subdivision.

The table below gathers the village's charges and reviews for a new house in one place. Fees change, so we confirm each one with the village before a client's budget is final.

Village of Northbrook charges and reviews for a new single-unit home (2026)
ItemWhat the village requiresWhen it applies
Demolition tax$10,000, not refundableTeardowns, due at demolition permit issuance
Demolition fees and deposit$750 in fees plus a $5,000 right-of-way deposit and escrow, refunded after final inspectionTeardowns, due at permit issuance
Permit application deposit$1,000When the building permit application is submitted
Building construction and inspection fee$3.00 per square foot of floor areaBefore the building permit issues
Impervious coverage fee$1.60, $0.80 or $0.00 per square foot of new hard surface, by areaNew hard surface on former lawn
Stormwater detentionUnderground detention with a sealed stormwater report1,000 square feet or more of new impervious surface
Monotony housing reviewPhotos of the three houses on each side and the one across the streetEvery new single-unit house
Fire sprinklersSeparate fire protection permit, issued before rough framing inspectionEvery new house

Village of Northbrook: Residential Demolition page, New Single-Unit Residence page, Civil Engineering Submittal Guidelines (2026), Impervious Coverage Fee sheet, Monotony Housing Review Application, Fire Protection Letter of Understanding

Step three: the permit submittal and what reviewers check

The building permit application asks for more than drawings. The new residence page lists a zoning worksheet, a building site and utility data worksheet, a whole house mechanical ventilation worksheet, solar and EV-ready provisions, a fire protection letter of understanding and a monotony housing review application. Fees are a $1,000 permit application deposit when you submit and a building construction and inspection fee of $3.00 per square foot of floor area before the permit issues. On a 5,000 square foot house, that fee alone is $15,000.

The monotony review surprises people. Under the village's monotony housing review application, you submit labeled color photos of the three houses on each side of yours and the house directly across the street, and staff can deny elevations that are too similar to a neighboring house. Once approved, any change to the exterior design goes back for review. Because our architects and builders sit on one team, we design the elevations with that review in mind and price any exterior change before it is made.

The village also lists the most common reasons residential plans stall, on its plan submission mistakes page: title blocks not signed by a licensed design professional, site plans not drawn to scale, missing design loads, and missing insulation and ventilation details. A complete first submittal is the best schedule protection we know. Our custom home architects prepare the drawings with the builders who will use them.

During construction: drainage, sprinklers and site rules

Before work starts, Public Works holds a pre-construction drainage meeting on new homes. The rules from that sheet carry through the whole job: silt fence stays until sod or at least 75 percent grass growth, no materials stored in the right-of-way or within 10 feet of it without an approved site plan, wet saws for masonry, and neighbors told at least 10 days before any utility work on their property, with restoration within 5 days.

Fire sprinklers are required in every new house. The village's fire protection letter of understanding requires a separate sprinkler permit, approved before the rough framing inspection can be scheduled. If it is not, that inspection is cancelled, which is why we file the sprinkler permit alongside the building permit.

Construction noise is allowed Monday through Friday from 7 a.m. to 7 p.m. and Saturday from 9 a.m. to 5 p.m., with none on Sunday, according to the village's building permits page.

How we run a Northbrook build as one team

On a Northbrook home, the architect, the civil engineer's coordination, the interior designer and the builder all answer to one plan. Nobody hands you from a salesperson to a designer to a project manager. The person who walked the lot with you is in the meeting when the grading plan comes back, and the builder who will pour the foundation has already reviewed the drawings.

For budgeting, in our experience custom homes run $250 to $600 or more per square foot, and the village charges above sit on top of that. Our guide to the cost to build a custom home in Chicago breaks the number down, and our North Shore permit guide compares Northbrook with neighboring villages.

Common questions about building in Northbrook

Is the Northbrook demolition tax refundable?

No. The $10,000 demolition tax is due when the permit issues. Only the $5,000 right-of-way damage deposit and demolition escrow comes back, after the final demolition inspection is approved.

Does a new house in Northbrook need fire sprinklers?

Yes. The village requires fire protection systems in all new buildings, under a separate permit that must be issued before the rough framing inspection.

What is the monotony review?

A staff review of your elevations against the neighboring houses. You submit photos of the three homes on each side and the one across the street, and a design too similar to a neighbor can be denied.

When does Northbrook require stormwater detention?

When new impervious surface on the property reaches 1,000 square feet or more. Detention is then built underground on your lot, designed by your civil engineer.

Can we remove trees before we apply?

No. Every removal must be approved by the Village Tree Preservation Officer first, and the tree survey covers your lot, 25 feet into the neighbors' lots and the right-of-way.

Start with the lot

If you are weighing a lot or a teardown, we will walk it with you and tell you what it can hold before you commit. Learn more about our work as a custom home builder in Northbrook, or request a consultation and our team will start with your lot.

Ben Amrami

Written by Ben Amrami

Last updated: November 26, 2026

With decades of experience and industry connections, Ben has a passion for problem-solving and takes pride in creating beautiful homes with superior value. He supervises every step of each project.

More insightsSee our work
Custom home interior by Amrami Design + Build

Thinking about building?

Bring your lot, your wish list, or just your questions. The first conversation is with the team that will design and build it, and it is free.

Request a consultation
773.842.11428248 Christiana, Skokie, IL 60076

© 2026 Amrami Group · Some project photos are digitally enhanced.